Tuesday, January 26, 2016

Order stuff and Devinyl left leading edge skin - 1 hour



Progress has come to a grinding hault. I've simply run out of clecos so I have been waiting to get the bonus from work to put in the big order...which finally came. Also took time off from the build to go skiing in the mountains last weekend. So now was the time to get all the things that I need to continue;
From Vans - 500 clecos, 2 flop tubes and plates for aerobatic tanks, safety wire, keyed deluxe fuel caps, Conduit, Proseal, Polygone Gel and a fuel tank test kit.
From Cleveland Tools - Mini Tungsten bucking bar, Electrical Crimpers, Reamers, 6" cobalt drill bit, Edge Roller tool, fly cutter, vise grip dimpler.
Misc - Weight scale, small spatulas.
Put the orders in....Should take some time to get here.
I decided to jump back into it by working on the leading edges. I started to devinyl the left leading edge skin.


No comments:

Post a Comment