Saturday, May 21, 2016

Even more tank prep - 7 hours

A big day at it finally!! I finished up preping the odds and ends with the nylon wheel.
I finished the tank access stiffeners and the outboard rib stiffeners.




One important item that I wanted to take care of was ensuring that all of the tank nose ribs where cleaned up had proper rib flange faceting as noted in the Van's manual. Darin, another local builder had warned me how important this was to have a clean and smooth leading edge. So I was very diligent to not be cavalier with this step.
I used files (flat and round) to take down the sharp edges and them smoothed them with scotchbrite on the 3M wheel.  

I then deburred all the holes in the ribs. This is not an easy process. Accessibility to the flange rivet holes is fine, but getting to the inside is another story. The leading edge ribs are not fun as the tight fit/clecos have a tenancy to make more pronounced burrs that don't come off easily. I ended up using a combination of a light deburr and a once over with  scotchbrite on the dremel to ensure no burrs.
Finally I was ready to dimple the ribs with the tank dies.


Then it was the same process on the stiffeners. Clean, deburr, nylon wheel, dimple.



Friday, May 20, 2016

More final tank prep - 2.5 hours

Once I was happy with the matting surface of the skin with a few second passes over here and there it was time to dimple with the tank dies.
 
I made quick work of the tanks skins. Next was to start the prep work on the ribs. I traced out the necessary areas on the ribs and miscellaneous pieces and went to work with the nylon brush and the cordless drill.
 







Thursday, May 19, 2016

Final tank prep - 3.5 hours

Its funny when you say that you are ready to proseal but really there is still much to do. There is lots of holes to debur. This gets to be a long process. I managed to do the left skin and after have very sore fingers!

I need to go over each area where proseal makes contact with a nylon wheel brush. I used the air drill but soon found that the compressor just couldn't keep up and was running quite hot and the air was getting moist (the air dryer couldn't keep up). So I ditched the pneumatic drill in favor of the electric drill.

Takes a bit of getting used to to ensure good coverage and straight lines but I was successful in the end. The first pass is made, and then a second pass is done to form a criss-cross pattern. The key is to try to keep your lines/passes straight, while applying just enough pressure to score the aluminum but not dig too deep. Its easy to maintain the right pressure, but a little more tricky to hold it straight.
Going slow helps a lot. 


I managed to prep the skins of both tanks.

Tuesday, May 17, 2016

Right tank skin prep - 2 hours

Still battling a lack of desire to build (now that spring is here and there is so much outside work to do), I managed to get a couple of hours of work in on the right tank skin. First order of business is to de-vinyl the outside tank. Then, I deburred. Once I was happy with all of that. I wiped down everything with MEK.

Its getting late and I'm yawning.

Monday, May 16, 2016

Finishing new anti-hangup bracket - 1 hour

Managing to find a little bit of desire to build today, I managed to cleco up the other fuel tank and fabricate the new anti-hangup bracket. Much easier this go around as I already have the paper template drawn out and the 1/2" wide material.

Sunday, May 15, 2016

Creating a new anti-hangup braket - 3 hours

I am zapped of all energy from the weekend. Had a house party on Saturday, and it was three days of prep and cooking, followed by a late evening.

I managed to gather enough strength to began fabrication on another anti-hangup bracket. I had to cut more 0.025" material at 1/2" thick. I cut a paper template and tried again. This time,Ii referenced another build log and twisted the bracket so that it ended up slightly back from the original position.



This way is a bit more challenging to fit but I made it work with using the holes that I had drilled before. Just really had to go slow and work at it. No quick work here. The result was excellent.

Only one small item that I noticed. At one point of the fittings, it had a tenancy to grab a little on the stiffener. I'll have to take a better look at this with Mike.

Thats enough for today. I'm spent!

Tuesday, May 10, 2016

Testing the inner anti-hangup - 1 hour

When looking over all the build log photo's of the fuel tanks, I noticed that most folks didn't have a inner anti-hangup bracket like mine. It occurred to me that I did not test the full movement of the fuel pickup. It was bothering me, to I re-cleco'd the assembly just to check. Well wouldn't you know. There was an issue with the anti-hangup bracket. At one point the sharp edge of the bracket makes contact with the rubber ring on the pick up. Well...My fear was realized. Back to the drawing board.


I will have to create another setup.